Preparing the Site for a Timber Frame Delivery and Crane Day

Home

Crane day is exciting; it means all of your hard work has started to resemble a building. It is also one of the easiest days to mess up if you have not sorted access, ground conditions or paperwork. Preparation can mean the difference between a simple installation and additional charges. For Timber Frame House Kits, visit https://merlintimberframe.co.uk/timber-frame-kits/

  1. Confirm the plan in writing

Request these details from your timber frame supplier:

Delivery date and arrival window

Lorry size and turning requirements

Kind of crane, lift plan and place for the installation

What is to be done on site (sign off on foundations, sole plates, etc)

  1. Make access simple

Before the lorry arrives:

Reinstate the path from the street to the set-down area

Be aware of height restrictions, trees, overhead cables and any tight turns

If necessary, organise parking suspensions or traffic management

Alerting neighbours cuts down the surprise factor when the crane arrives.

  1. Make the ground stable for heavy vehicles

A lorry and crane are both very heavy when loaded. Make sure:

Entrance and hardstanding can handle the weight

All soft ground is protected with mats or a temporary trackway

There is space for outriggers and safe working zones.

  1. Establish a landing and storage area

A flat, dry area for panels and materials. You want it within lifting distance but not too close.

  1. Optimise your site for developing straightaway

Organise labour, site tools and welfare. Waiting time and/or re-delivery may be charged if the frame cannot be put up upon delivery.

If you are not sure, then ask the supplier for a pre-delivery checklist. This is what they use to ensure that crane day runs smoothly.